Since implementing the GW FIM Procedures Manual, we have learned some lessons and noticed trends. For example, one of the most common misconceptions I encounter is that FIM is analogous to BIM. As the George Washington University Division of Operations nears the one year anniversary of its implementation of the GW FIM Procedures Manual, I feel now is as good a time as any to address some of the misconceptions, answer common questions, and speak to some of the lessons learned in this first year.
What is FIM?
FIM – our acronym for Facilities Information Management – is GW’s approach to capturing information on all new construction, renovations, repairs, upgrades, and equipment replacement projects, and leveraging it for building lifecycle facilities management. The FIM Procedures Manual outlines our requirements for BIM, 2D CAD, O&M manuals, and our asset information exchange table, while also laying out the responsibilities of designers, builders, and GW employees for all project types.
Is FIM the same as BIM?
No, BIM and FIM are not the same thing. The FIM Procedures Manual provides requirements for BIM projects while also giving requirements for other non-BIM projects. All projects – new construction, renovation, upgrade, repair, and equipment replacement – are FIM projects, but not all of those projects require BIM.
What are vital things project teams should know early?
It’s best if everyone on a project team is familiar with the GW FIM requirements in order to ensure the most desired outcomes. That said, items related to project setup – BIM Execution Plan, file naming conventions, drawing number requirements – are a hassle to change midstream, so it is most convenient for designers to avoid all the extra work associated with having to change file/model names, drawing numbers, etc. For builders, knowing file naming conventions and O&M requirements before beginning work will make certain things run more smoothly, especially for any parts of O&M manuals that would be prepared by subcontractors.
What are the differences between BIM and non-BIM projects?
The GW FIM Procedures Manual has a chart on page 4 highlighting which manual sections do not apply for non-BIM project deliverables. Additionally, charts listing designer and contractor deliverables for BIM and non-BIM projects can be found on manual pages 63-66.
Must designers change their CAD layering standards to comply with the Space Layering Template?
No, designers do not need to change internal CAD layering standards to comply with the Space Layering Template. The Form 6 – DWG Space Layering Template only applies to any space plans the designer is producing, but all other drawings can use whatever layering standards the designer chooses to use.
How does GW intend to use record models handed over during project closeout?
GW seeks to compile the most accurate data possible for its facilities, and part of that effort includes creating an inventory of building information models. As of right now, our CAFM does not support bi-directional linking between it and BIM, hence the requirement for asset data to be delivered in formats other than embedded in models. The GW FIM Procedures Manual is the first step of implementation of new processes and technologies, and we anticipate incorporating lessons learned as more projects are completed using these requirements. For right now though, GW intends to use record models for space management and to depict an accurate representation of the built condition in our facilities.
How often should project teams meet to discuss progress/compliance with the FIM Procedures Manual?
My recommendation would be to make FIM compliance a regular agenda item at all project meetings, even if only to say “let’s go around the table and everyone give me a quick report on your FIM deliverable progress.” With that said, project teams should, at a minimum, discuss FIM deliverable progress and compliance at the following benchmarks:
- Pre-bid conference – to get answers for questions that could affect bids
- Project kickoff – ensure the design team knows the requirements
- Construction kickoff – ensure the contractor knows the requirements and can notify subcontractors
- Closeout kickoff – roughly halfway through the construction process so the project team can determine what steps must be taken in order to achieve all desired outcomes and meet deadlines.
The GW FIM Procedures Manual is a departure from project requirements of the past, and there is an understanding that its implementation will come with a learning curve and some lessons. With this learning curve, it is important to remember that communication, coordination, and managing the process are keys to success.
-JLF